The Gospel Oak to Barking electrification works that were meant to finish last month have been delayed until January 2018
The £130m upgrade of the Gospel Oak to Barking line on the London Overground that was due to be finished last month won’t be finished until January next year, Network Rail announced today.
Transport for London had said in May last year that the electrification work would finish by the end of this June, but Network Rail said today that it now expects the installation to be completed in January 2018.
Read more: Gospel Oak-Barking line set for summer closures after upgrade delays
That will then be followed by testing of the new electric trains and driver training, with trains entering passenger service from spring 2018. The current diesel services will run as normal until they are replaced by the new double-length trains.
Along the 14-mile route, a number of the structures carrying the overhead lines were incorrectly designed and couldn’t be installed at the planned locations. Further delays were caused by late delivery of materials and structures.
Jonathan Fox, TfL’s director of London Rail, said: “We have been working closely with Network Rail to ensure their remaining work to electrify the Gospel Oak to Barking line is finished as soon as possible to minimise the disruption to our customers and to avoid delay to the introduction of new electric trains next year.”
Upcoming closures
Weekend closures will take place from Saturday 29 July to Sunday 10 September, while Network Rail said discussions are ongoing to finalise dates for additional weekend closures this autumn, and two longer closures needed to complete electrification.
The longer closures are proposed to be:
Sunday 17 September – Sunday 22 October
Monday 27 November – Sunday 14 January
The dates will be confirmed nearer the time though. Network Rail said rail replacement buses will be provided, and regular users of the Gospel Oak to Barking line will continue to be automatically refunded the additional cost of travel made by Tube or rail.
Network Rail’s route managing director Meliha Duymaz said:
This project has not been without its difficulties and we’d like to apologise for the continued disruption and thank both passengers and neighbours for their patience while we finish our work.
We still have a lot to do but with a new team in place to finish off the project, I’m confident that the immense benefits of this once-in-a-lifetime investment will be realised in the months ahead, and the benefits enjoyed for years to come.
Caroline Pidgeon, Liberal Democrat London Assembly member, said the announcement made for “depressing news for the long-suffering users of this line”.
“A year ago Network Rail were predicting that closures on the line will finally come to an end by June 2017,” she said.
To now discover that in addition to weekend closures this summer there will also be two further block closures of the line is depressing news for the long-suffering users of this line.
In addition to ensuring train users are properly compensated it is time that Network Rail came clean and properly explained how this electrification programme has been so appallingly managed.
Read more: Gospel Oak to Barking electrification to miss deadline as delays pile up